  2012 2013 2014 2015
Data Development January 2 - December 31, 2012      
Ecoregional Team Development March 1 - October 15, 2012      
Target Criteria May 1, 2012 - January 15, 2013    
Threats and Stressors April 27, 2012 - January 31, 2013    
Ecoregional Workshops December 10, 2012 - July 26, 2013    
Data Compilation December 3, 2012 - April 30, 2013    
Statewide Strategies August 1 - September 30, 2013    
Conservation Strategies March 4, 2013 - June 30, 2014  
Public Scoping October 1 - November 27, 2013    
Public Review 1 October - November 2014  
Public Review 2 July - August 2015
Public Outreach August 2012 - July 2015
Companion Plans July 2014 - July 2015